During construction we can make several trips to the site.  The frequency is based on the specific project but the following list outlines some of the common stages to visit the site during construction.

Pre-construction meeting
Review drawings and answer any questions by the builder. We’ll take a look at the surveyor’s stakes and make sure they match the drawings.

Foundation Complete
Observe foundation installation, including waterproofing, footing drain, and foundation & slab insulation.

Rough Framing Complete
Check framing for compliance with the drawings.  Ensure that window placement is aligned with views as intended.

Insulation Installed
Observe insulation installation.  Insure that all voids are filled, including behind electrical and mechanical.

Drywall Complete
Check on the drywall installation.

Finishes
Observe finish installations.

Punch List
A review of the job to create the final Punch List for the builder.

Wilson Architects Inc. | www.w2arch.com

Advertisement

Leave a Comment so far
Leave a comment



Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s



Follow

Get every new post delivered to your Inbox.